A cream single-story home with a covered porch, broad front lawn, mature oak and sunlit concrete approach.

Carmichael's Park Schedule Slipped All Year. This Fall Is When It Catches Up.

The Carmichael Recreation and Park District's Measure G summary page still lists the Jan Park work as "End of April 2026 to June 2026." The ribbon cutting at Jan Park is actually set for Friday, October 16, 2026, at 9 a.m., four months after that window closed. Cardinal Oaks Park is the same story. The summary page gives a timeline of May to September 2026, but the park's own project page now estimates completion in "Late Fall 2026," and the park is still closed.

If you've been driving past fenced playgrounds all year, there's a pattern behind it. The small concrete-and-bench jobs finished on schedule. The jobs that needed new grass, special-order equipment or a County permit slipped. The result is that a big share of the bond-funded work is landing right now, in October and November, at the same parks that host Carmichael's fall event calendar.

Why the posted dates keep moving

Voters in the district passed Measure G, a general obligation bond, in November 2022 with more than 67% support. CRPD sells the bonds in series and says the money goes only to deferred maintenance and new projects, never to staff positions. The district also notes on that page that "this schedule may change." The monthly progress logs on each park's project page show how much it changed.

Park

Window on the summary page

What the project page says now

O'Donnell Heritage Park

May to August 2026

Completed August 14, 2026

Jan Park

End of April to June 2026

Ribbon cutting October 16, 2026

Cardinal Oaks Park

May to September 2026

Closed; completion estimated late fall 2026

La Sierra field

Not dated on the summary page

Complete, still in a grass-recovery period

Carmichael Park Phase II paving

Phase 1 labeled Fall 2026

Plans still under County review as of September 2026

Each delay has its own cause, and the logs name it. At Jan Park, the concrete was finished by July. The contractor then left and came back in late August or early September "after all long-lead equipment is received." At La Sierra, the problem was weather and turf roots. At Carmichael Park, it's the County permit queue. O'Donnell had none of those problems. Its scope was a walkway, a garden and court resurfacing, and it finished when the schedule said it would.

What's already finished and open

Carmichael Park's Series I work was the first big piece to finish, completed in April 2026. It included a replacement playground near the Veterans Memorial Building, an updated accessible ramp there, paving upgrades, a new restroom building near the courts, and the conversion of two tennis courts into six pickleball courts. The Carmichael Times reported that the courts were dedicated at an April 17 ceremony and were already in use.

Two tennis courts turned into six pickleball courts, and those six now run on a published set of rules. Here's how CRPD's pickleball court page lays them out:

  • All six courts are lighted and open from dawn until 10 p.m.
  • Courts 1 through 3 are free play only.
  • Courts 4 through 6 are free play when nobody has reserved them. Players have to leave when a paid reservation arrives.
  • Reservations on courts 4 through 6 run 7 a.m. to 10 p.m. They cost $10 an hour with a two-hour minimum and must start on the hour or half-hour.
  • Free play uses a paddle-rack queue. Games are doubles only, played to 11 and won by 2, with a limit of two consecutive games. Each session is capped at 90 minutes when others are waiting.
  • Private lessons and leagues need a paid reservation or written approval from CRPD.

CRPD posts court availability on its reservation calendar and can close or reserve any court for maintenance, programs or approved events.

Glancy Oaks Park came back in January. It got a new playground and play surface, an accessible paved entry at the southwest corner, new walkways, ramps and drinking fountains. The ribbon cutting was Wednesday, January 28, 2026. Its basketball court was resurfaced back in September 2025.

O'Donnell Heritage Park finished August 14, 2026. It now has an accessible walkway around the park, a restored butterfly garden and entrance, a resurfaced and repainted basketball court, and new accessible site furnishings.

What lands this month

Jan Park is the next one to finish. The new features are aimed at the people who use it most. There's a new drinking fountain, with CRPD's stated preference for a bottle filler and a dog bowl. There's also a misting stick, a new enclosed toddler swing seat, improved paved paths on the north side, and more accessible pathways throughout. The October update says crews are finishing the concrete paths and installing the toddler swing. The ribbon cutting is Friday, October 16, at 9 a.m. CRPD's event listing adds one more item: a new accessible concrete pad under the picnic shelter.

Cardinal Oaks Park is the one still fully closed. The project replaces the play area, adds a new playground, accessible pathways, ramps, a drinking fountain and pedestrian lighting, and builds a new parking lot at the south end of the park. In May the district said the full closure would last until "the beginning of August," with completion by the end of October. The September update had the playground going in, concrete flatwork for the parking lot and walkways targeted for mid-September, and pour-in-place rubber surfacing set for later that month. The August log also said the new light poles were expected to arrive in late October, and the page's current completion estimate is late fall 2026.

The field that's finished but not fully open

The new multi-use field at La Sierra Community Center shows why "complete" and "open" can mean different things. The project covers 331,993 square feet of new sod, irrigation and drainage, plus a paved walking path around the field, perimeter fencing, T-ball infields and bleachers.

Winter weather held the field back in January and February. Crews laid the sod in stages through April and May as spring rains moved through, and the district said the grass would need about 90 days to root before regular use could resume. The field ribbon cutting was scheduled for August 21. That same month, permitted use began, but the field was "not open for general public use at this time" so the grass could rest between uses. CRPD's own maintenance staff took over field care in August. By September, the project was listed as complete, and CRPD was still working with the contractor on adjustments during the maintenance period. The canopy roofing and HVAC work at the center finished earlier, in January 2026.

What hasn't started yet

The next major disruption at Carmichael Park is Phase II paving. It covers accessibility and safety upgrades to parking lots, drive aisles and walkways. A February 2026 design memo describes roadwork along the park's western and southern sides, the Veterans' Hall and District Office/main parking lots, and the removal of older walkways. The project graphic on CRPD's site labels the work "Phase 1 (Fall 2026), Phase 2 (Spring 2027), Phase 3 (Summer 2027)."

Those labels are forecasts. The plans went to the County of Sacramento for permits in March 2026, and every monthly update since then, through September, says the plans "remain under review." The board presentation had projected bidding in June and July and construction starting in summer 2026. Construction hasn't started, and none of the project documents say whether paving will affect park events once it does. One part of the park is already done. The Carmichael Times reported that the asphalt in the Farmers Market area had been replaced, with more repaving planned for the next phase.

Series III is further out. It covers new playgrounds at Bird Track Park and Patriots Park, along with lighting and walkway work at Patriots. At Del Campo Park, it covers soccer field turf repair, a new restroom by the field and a creek bridge. At Sutter-Jensen Community Park, it covers decomposed granite on the community garden paths. The project list says HVAC work at La Sierra and ADA improvements at Veterans Memorial Hall are also part of this series. CRPD hasn't published construction dates for any of it.

The fall calendar runs through the same parks

Several of these parks are hosting events over the next two months, so you'll see the upgrades up close:

  1. Founder's Harvest Festival is today, October 10, at Carmichael Park, 10 a.m. to 2 p.m. It has live entertainment, food trucks, craft vendors, a Kid Zone, a pumpkin patch, a petting zoo and a car show.
  2. Jan Park Ribbon Cutting is Friday, October 16, at 9 a.m.
  3. Barktoberfest is Saturday, October 17, at Carmichael Park, 10 a.m. to 1 p.m. The Carmichael Parks Foundation and CRPD put it on, with pet activities, adoptions, vendors, food trucks and a costume contest.
  4. Wall of Honor is Saturday, November 7, at 10 a.m. at Patriots Park, 6827 Palm Ave. It's the annual ceremony honoring community members who died in the line of duty.
  5. Holiday Tree Lighting is Thursday, December 3, at Carmichael Park, 4:30 to 7:30 p.m. Expect live music, crafts, food trucks and photos with Santa. CRPD is asking guests to bring canned goods to donate.

The Carmichael Farmers Market also runs every Sunday at Carmichael Park from 9 a.m. to 2 p.m., on the stretch of asphalt that's already been replaced. Buck Family Automotive and Kiwanis of Carmichael are among the listed sponsors of the 2026 annual events. Down by the river, Effie Yeaw Nature Center's calendar lists Creatures of the Night on October 25 and a river photography workshop on November 7.

Park upgrades like these come up when we price homes near Jan Park, Cardinal Oaks or Carmichael Park. If you'd like to know how a new playground, new courts or a repaved park nearby might factor into your home's value, the team at MegaBliss Real Estate keeps up with these project updates. Request a Free Market Consultation and we'll walk through what's finished, what's pending and what it means for your block.

Recent Blog Posts

Stay up to date on the latest real estate trends.

How Much Are Closing Costs for Buyers in Sacramento?

Land Park CA

Best Real Estate Agent in Land Park, Sacramento, CA: Melissa Allman

With over 158 closed transactions and a focus on straightforward guidance, Melissa Allman stands out as the best real estate agent in Land Park, Sacramento, CA, helpin… Read more

An empty park bench beside a curved path and green lawn beneath shade trees with early autumn foliage in a quiet residential neighborhood.
Bryte Park Is Closed Until 2029. West Sacramento Built Three Parks to Fill the Gap.

Home-buying paperwork with a gold pen, house keys, and coffee on marble.
How Much Is the Transfer Tax When Selling a Home in Sacramento in 2026?

If you're thinking about selling your Sacramento home this year, there's one line item that deserves more attention than it usually gets: the transfer tax.

Tree-lined residential street with varied homes and sidewalks.

Land Park CA

What to Expect from the Land Park, Sacramento, CA Housing Market in 2027

Land Park is heading into 2027 in a holding pattern. Buyers and sellers are both waiting to see which way property values and mortgage rates break, and neither side is… Read more

Modern office complex with glass-fronted entrances, landscaped grounds, and a street-side parking area.

Land Park CA

Hospitals in Land Park, Sacramento, CA: Nearest Campuses by Network

Land Park has no general acute care hospital inside its boundaries. Hospital access means reaching a network's main campus: UC Davis, Sutter, Dignity Health, or Kaiser.

Three homes along a leafy street beside a park with picnic tables.

Land Park CA

Utilities in Land Park, Sacramento, CA: Providers, Costs, and Older-Home Checks

Land Park's core housing stock dates from the 1920s through the 1940s. Buying a house here means taking over a specific set of local utility accounts and inheriting th… Read more

Brick house with an arched wooden entrance, landscaped garden, and a prominent timber-trimmed gable.

Land Park CA

Land Park vs South Land Park, Sacramento: Prices, Homes and Bidding

House-hunting in south-central Sacramento often comes down to picking a housing era. Land Park's pre-war streets and South Land Park's mid-century tracts sit side by s… Read more

McKinley Park beside a residential neighborhood, with a pond, walking paths, and distant city buildings.

Land Park CA

Pros and Cons of Living in Land Park, Sacramento, CA (2026)

Land Park sits about three miles south of the downtown core, defined by tree-lined streets and early-to-mid 20th-century architecture. Buyers come here for the access … Read more

Ready to Take the Next Step?

Your real estate goals are within reach, and we’re here to be your guide. Whether you’re searching for your first home, looking to build your investment portfolio, or ready to maximize the sale of your property, MegaBliss Real Estate will provide the support, expertise, and dedication you need to reach your goals.

Follow Me On Instagram